Beaver Creek Project Construction Schedule

Construction for the the Beaver Creek Clean River Project includes five phases beginning in Spring of 2021 until Project completion in December 2022. Please check this page for updates to the construction schedule, or sign up to receive updates.overview map

  1. Rebecca Caldon, P.E.

    Engineering
    Phone: 518-434-5104

Two Week Look Ahead

Treatment Facility (Phase 5) and Diversion Pipe (Phase 3)

Timeframe

Work 

Impacts

April 7 - April 23Pre-construction, tree removals lane closures
May 10, 2021 - Fall 2022Excavation and tunneling Closure of road from TOAST Elementary to MLK Jr. Blvd. Temporary Traffic Pattern (shown below) 


Lincoln Park Bowl Athletic Field (Phase 5)

Timeframe

Work 

Impacts

May 2021 - May 2022 Fill added. Regrading of fields and new grassClosure of eastern half of Bowl and Lincoln Park Road (south)
May 2021 - May 2023Fill added. Regrading of fields and new grass
Closure of southwest quarter of Bowl and Lincoln Park Road (south)
September 2021 - May 2023 Fill added. Regrading of fields and new grass
Closure of northwest quarter of Bowl and Lincoln Park Road (south)


Lincoln Park Ravine (Phase 3)


Timeframe

Work 

Impacts

April 7 - April 14Tree/brush removalReduced access
Summer 2021Grading ImprovementsReduced access
Fall 2022Reinstall Community GardenReestablished and improved
2022Design of Ravine GardenFuture Improvement


Third Ave and Pearl St. (Phase 1)


Timeframe

Work 

Impacts

April 19 - May 31Pre-constructionLane closures
May 31 - July 2Installation of Diversion StructureLane and parking closures

Temporary Traffic Pattern at TOAST Elementary for Duration of Construction.

Temporary Traffic Pattern