This page contains all information pertaining to the 2021 Contract II Street Resurfacing and Sidewalk Reconstruction Project.
Blue Bell Lane (Lower) Shaker Park Drive to Dead End
Mill and Fill, Wedge Curb Reconstruction
300 feet
Loudonville Road Loudonville Road Bridge to North Pearl Street
Mill and Fill
1,430 feet
Shaker Park Drive Pilgrim Drive to Kerry Lane
Mill and Fill
1,050 feet
McArdle Avenue Livingston Avenue to Beverley Avenue
Mill and Fill, Minimal Curb Reconstruction, Partial Sidewalk Repair
700 feet
Second Street North Swan Street to Lark Street
Mill and Fill, Minimal Curb Reconstruction, Partial Sidewalk Repair
1,400 feet
Spring Street Dove Street to Lark Street
Mill and Fill, Partial Curb Reconstruction, Partial Sidewalk Repair
730 feet
Jeanette Street Second Avenue to Delaware Avenue
Mill and Fill, Partial Curb Reconstruction, Partial Sidewalk Repair
730 feet
Joelson Court Whitehall Road to Hackett Boulevard
Mill and Fill, Partial Curb Reconstruction, Partial Sidewalk Repair
1,060 feet
Rose Court Whitehall Road to Hackett Boulevard
Mill and Fill, Partial Curb Reconstruction, Partial Sidewalk Repair
1,030 feet
Hunter Avenue Watervliet Avenue to North Manning Boulevard
Mill and Fill, Minimal Curb Reconstruction, Partial Sidewalk Repair
1,810 feet
Rosemont Street Washington Avenue to Dead End
Mill and Fill, Wedge Curb Reconstruction, Partial Sidewalk Repair
1,030 feet
Hawthorne Avenue Belvidere Avenue to Melrose Avenue
Mill and Fill, Full Curb Reconstruction, Partial Sidewalk Repair
870 feet
Ormond Street Western Avenue to Cortland Street
Mill and Fill, Partial Curb Reconstruction
1,250 feet