Beaver Creek Project Construction 

Construction for the the Beaver Creek Clean River Project includes five20220422 Tunnel phases beginning in Spring of 2021 until Project completion in March 2023. Please check this page for updates to the construction schedule, or sign up to receive updates

  • Phase 1 – Completed July 2022
  • Phase 2 – Completed August 2022
  • Phase 3 – Completed April 2022
  • Phase 4 – Completed June 2022
  • Phase 5 – Construction April 2021 – March 2023

View an interactive map that shows the Project's tunneling progress, photos, and aerial images. 

Copy-of-20220726_Schedule

Beaver Creek Clean Water Project Schedule Overview